Bronx Street Tree Planting FY16 - Community Boards 9-12

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will plant new trees in Community Boards 9-12 in the Bronx.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: March 2015
Projected Completion Date: May 2015
Completion Date: May 2015

Procurement

Start Date: May 2015
Projected Completion Date: February 2016
Completion Date: December 2015

Construction

Start Date: March 2016
Projected Completion Date: September 2017
Completion Date: August 2017

Understand how we build parks.

Funding

Total Funding: $1,495,000
Funding Source: Mayoral

Location

Various locations in the Bronx

Project Staff

Contact NYC Parks about this project

Last updated: 11/22/2024