Queens Street Tree Planting FY16 - Community Boards 9,10,13,14

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will plant new trees in Community Boards 9, 10, 13 & 14 in Queens.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: March 2015
Projected Completion Date: May 2015
Completion Date: May 2015

Procurement

Start Date: May 2015
Projected Completion Date: February 2016
Completion Date: April 2016

Construction

Start Date: May 2016
Projected Completion Date: October 2017
Completion Date: April 2017

Understand how we build parks.

Funding

Total Funding: $1,250,000
Funding Source: Mayoral