Queens Street Tree Planting FY16 - Community Boards 9,10,13,14
-
100% complete
-
100% complete
-
100% complete
This project will plant new trees in Community Boards 9, 10, 13 & 14 in Queens.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: March 2015
Projected Completion Date:
May 2015
Completion Date:
May 2015
Procurement
Start Date: May 2015
Projected Completion Date:
February 2016
Completion
Date:
April 2016
Construction
Start Date: May 2016
Projected Completion Date:
October 2017
Completion Date: April 2017
Understand how we build parks.
Funding
Funding Source: Mayoral
Last updated: 11/22/2024