Project Timeline
Design
Assigned & Start Date: March 2015
Projected Completion Date:
May 2015
Completion Date:
May 2015
Procurement
Start Date: May 2015
Projected Completion Date:
February 2016
Completion
Date:
February 2016
Construction
Start Date: March 2016
Projected Completion Date:
September 2017
Completion Date: September 2017