Highland Park Basketball Courts Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct four basketball courts in Highland Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: July 2015
Projected Completion Date: June 2016
Completion Date: January 2017

Procurement

Start Date: January 2017
Projected Completion Date: October 2017
Completion Date: December 2017

Construction

Start Date: March 2018
Projected Completion Date: March 2019
Completion Date: February 2019

Understand how we build parks.

Funding

Total Funding: $836,000
Funding Sources:
  • City Council
  • Mayoral

Location

Highland Park, Queens
Jamaica Avenue at Cleveland Street
Community Board: 05, 05

 

Project Staff

Project Liaison: Meira Berkower
Contact NYC Parks about this project

Last updated: 01/17/2025