Pelham Bay Park Service Building Gas Line Construction and Heating System Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will install a new gas service line, remove oil tanks, and convert the building from oil to gas heat.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: November 2014
Projected Completion Date: July 2015
Completion Date: May 2016

Procurement

Start Date: May 2016
Projected Completion Date: February 2017
Completion Date: July 2017

Construction

Start Date: March 2018
Projected Completion Date: March 2019
Completion Date: March 2019

Understand how we build parks.

Funding

Total Funding: $1,213,000
Funding Source: Mayoral

Location

Pelham Bay Park, Bronx
South side of City Island Road between Shore Road and Park Drive
Community Board: 10, 12

 

Project Staff

Project Liaison: Katerine Borrome
Contact NYC Parks about this project