Buono Beach Fountain Reconstruction (Hurricane Sandy)
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct the electrical and mechanical components of the fountain at Buono Beach in Alice Austen Park.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: July 2015
Projected Completion Date:
March 2017
Completion Date:
November 2019
Procurement
Start Date: November 2019
Projected Completion Date:
August 2020
Completion
Date:
September 2022
Construction
Start Date: October 2022
Projected Completion Date:
October 2023
Completion Date: October 2023
Understand how we build parks.
Funding
Funding Sources:
- City Council
- Federal
- Mayoral
- State
Location
Alice Austen Park, Staten Island
Edgewater Street between Hylan Boulevard and Clifton Avenue
Community Board: 01