Buono Beach Fountain Reconstruction (Hurricane Sandy)

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the electrical and mechanical components of the fountain at Buono Beach in Alice Austen Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: July 2015
Projected Completion Date: March 2017
Completion Date: November 2019

Procurement

Start Date: November 2019
Projected Completion Date: August 2020
Completion Date: September 2022

Construction

Start Date: October 2022
Projected Completion Date: October 2023
Completion Date: October 2023

Understand how we build parks.

Funding

Total Funding: $1,203,000
Funding Sources:
  • City Council
  • Federal
  • Mayoral
  • State

Location

Alice Austen Park, Staten Island
Edgewater Street between Hylan Boulevard and Clifton Avenue
Community Board: 01

 

Project Staff

Project Liaison: Joseph Homsey
Contact NYC Parks about this project

Last updated: 11/22/2024