Idlewild Park Forest Restoration and Tree Planting

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will prepare planting sites for invasive species removals including the planting of new and replacement trees at Idlewild Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: January 2015
Projected Completion Date: February 2015
Completion Date: February 2015

Procurement

Start Date: February 2015
Projected Completion Date: November 2015
Completion Date: November 2015

Construction

Start Date: November 2015
Projected Completion Date: May 2018
Completion Date: December 2018

Understand how we build parks.

Funding

Total Funding: $1,896,000
Funding Source: Private

Location

Idlewild Park, Queens
Rockaway Boulevard between 183rd Street and Brookville Boulevard
Community Board: 13

 

Project Staff

Contact NYC Parks about this project

Last updated: 10/11/2024