Citywide Ballfield Lighting Installation (CNYG-2815M)
-
100% complete
-
100% complete
-
100% complete
This project will install energy efficient ballfield lighting retrofits at various parks facilities citywide.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: December 2014
Projected Completion Date:
March 2015
Completion Date:
March 2015
Procurement
Start Date: March 2015
Projected Completion Date:
December 2015
Completion
Date:
June 2016
Construction
Start Date: September 2016
Projected Completion Date:
September 2019
Completion Date: July 2018
Understand how we build parks.
Funding
Funding Source: Mayoral
Locations
-
Astoria Park, Queens
Astoria Park South, 21 Street, Hoyt Avenue, Ditmars Boulevard, East River
Community Board: 01 -
Frederick B. Judge Playground, Queens
111 Avenue, 134 & 135 Streets, Lincoln Street
Community Board: 10 -
Haggerty Park, Queens
S/s Jamaica Av Bet 202 and 204 Sts
Community Board: 12 -
Roy Wilkins Recreation Center, Queens
Northwest of Fence Running from 118th Road to Hospital
Community Board: 12 -
Whitey Ford Field, Queens
26 Ave., 2 St.
Community Board: 01