Austin, Giovanelli, and Utopia Playgrounds Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the play areas at Ehrenreich-Austin Playground, Utopia Playground, and Giovannelli Playground.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: November 2014
Projected Completion Date: February 2016
Completion Date: March 2016

Procurement

Start Date: March 2016
Projected Completion Date: November 2016
Completion Date: January 2017

Construction

Start Date: February 2017
Projected Completion Date: February 2018
Completion Date: December 2017

Understand how we build parks.

Funding

Total Funding: $2,142,000
Funding Sources:
  • Borough President
  • Mayoral

Locations

 

Project Staff

Project Liaison: Meira Berkower
Contact NYC Parks about this project

Last updated: 01/17/2025