Austin, Giovanelli, and Utopia Playgrounds Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct the play areas at Ehrenreich-Austin Playground, Utopia Playground, and Giovannelli Playground.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: November 2014
Projected Completion Date:
February 2016
Completion Date:
March 2016
Procurement
Start Date: March 2016
Projected Completion Date:
November 2016
Completion
Date:
January 2017
Construction
Start Date: February 2017
Projected Completion Date:
February 2018
Completion Date: December 2017
Understand how we build parks.
Funding
Funding Sources:
- Borough President
- Mayoral
Locations
-
Ehrenreich-Austin Playground, Queens
Austin Street between 76 Avenue & 76 Drive
Community Board: 06 -
Forest Park, Queens
Myrtle Avenue, Union Turnpike, Park Lane South
Community Board: 05, 05, 06, 09 -
Utopia Playground, Queens
Utopia Parkway & 73rd Avenue
Community Board: 08
Project Staff
Project Liaison: Meira Berkower
Contact NYC Parks
about this project
Last updated: 01/17/2025