Sunset Cove Park Saltwater Marsh and Coastal Upland Construction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will construct a salt marsh and upland coastal forest area in Sunset Cove Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: March 2014
Projected Completion Date: November 2015
Completion Date: May 2016

Procurement

Start Date: May 2016
Projected Completion Date: February 2017
Completion Date: March 2018

Construction

Start Date: June 2018
Projected Completion Date: June 2019
Completion Date: June 2019

Understand how we build parks.

Funding

Total Funding: $10,410,000
Funding Sources:
  • Federal
  • Mayoral
  • Private

Location

Sunset Cove Park, Queens
south of West 19th street between Jamaica Bay and Cross Bay Boulevard
Community Board: 14

 

Project Staff