Sunset Cove Park Saltwater Marsh and Coastal Upland Construction
-
100% complete
-
100% complete
-
100% complete
This project will construct a salt marsh and upland coastal forest area in Sunset Cove Park.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: March 2014
Projected Completion Date:
November 2015
Completion Date:
May 2016
Procurement
Start Date: May 2016
Projected Completion Date:
February 2017
Completion
Date:
March 2018
Construction
Start Date: June 2018
Projected Completion Date:
June 2019
Completion Date: June 2019
Understand how we build parks.
Funding
Funding Sources:
- Federal
- Mayoral
- Private
Location
Sunset Cove Park, Queens
south of West 19th street between Jamaica Bay and Cross Bay Boulevard
Community Board: 14
Project Staff
Contact NYC Parks about this projectLast updated: 11/22/2024