Hamilton Fish Recreation Center and Pool Reconstruction

  • Design
    5% complete
  • Procurement
    0% complete
  • Construction
    0% complete

This project will reconstruct Hamilton Fish Recreation Center and Pool.

Project Notes

Project Update: Parks has reviewed stakeholder feedback and the scope of work for this project, and is now developing the design for the site.

Project Timeline

Design

Assigned & Start Date: May 2024
Projected Completion Date: May 2026

Procurement

The average time for procurement is 9-12 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Greater than $10 million
Funding Sources:
  • City Council
  • Mayoral

Location

Hamilton Fish Park, Manhattan
Pitt Street between Stanton Street and East Houston Street
Community Board: 03

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 11/22/2024