Clement Clarke Moore Park Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct Clement Clarke Moore Park.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: July 2015
Projected Completion Date:
January 2017
Completion Date:
May 2017
Procurement
Start Date: May 2017
Projected Completion Date:
February 2018
Completion
Date:
April 2018
Construction
Start Date: July 2018
Projected Completion Date:
July 2019
Completion Date: June 2019
Understand how we build parks.
Funding
Funding Sources:
- City Council
- Mayoral
Location
Clement Clarke Moore Park, Manhattan
10th Avenue between West 21st Street and West 22nd Street
Community Board: 04