Shore Park and Parkway Field House Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct the field house at Shore Park and Parkway.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: April 2016
Projected Completion Date:
June 2017
Completion Date:
July 2017
Procurement
Start Date: July 2017
Projected Completion Date:
April 2018
Completion
Date:
March 2019
Construction
Start Date: April 2019
Projected Completion Date:
September 2020
Completion Date: November 2021