Brower Park Skate Park Element Installation

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will construct new skate park elements in Brower Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: March 2015
Projected Completion Date: June 2015
Completion Date: June 2015

Procurement

Start Date: June 2015
Projected Completion Date: March 2016
Completion Date: December 2015

Construction

Start Date: April 2016
Projected Completion Date: October 2016
Completion Date: July 2016

Understand how we build parks.

Funding

Total Funding: $56,000
Funding Sources:
  • Borough President
  • Mayoral

Location

Brower Park, Brooklyn
Brooklyn Avenue, Park Place and Kingston Avenue
Community Board: 08

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project