St. Mary's Playground Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will construct new play equipment, benches, and pavements at St. Mary's Playground.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: February 2014
Projected Completion Date:
June 2015
Completion Date:
December 2015
Procurement
Start Date: December 2015
Projected Completion Date:
September 2016
Completion
Date:
February 2017
Construction
Start Date: April 2017
Projected Completion Date:
April 2018
Completion Date: April 2018
Understand how we build parks.
Funding
Funding Sources:
- City Council
- Private
Location
St. Mary's Park, Brooklyn
Huntington Street and Smith Street
Community Board: 06
Project Staff
Project Liaison: Davey Ives