Henry Hudson Park Basketball and Handball Courts Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the basketball and handball courts at Henry Hudson Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: October 2015
Projected Completion Date: October 2016
Completion Date: December 2016

Procurement

Start Date: December 2016
Projected Completion Date: September 2017
Completion Date: August 2018

Construction

Start Date: October 2018
Projected Completion Date: October 2019
Completion Date: September 2019

Understand how we build parks.

Funding

Total Funding: $2,449,000
Funding Sources:
  • City Council
  • State

Location

Henry Hudson Park, Bronx
Kappock Street between Independence Avenue and Palisade Avenue
Community Board: 08

 

Project Staff

Project Liaison: Katerine Borrome
Contact NYC Parks about this project

Last updated: 11/22/2024