Williamsbridge Oval Skate Park Construction
-
100% complete
-
100% complete
-
100% complete
This project will construct a new skate park at Williamsbridge Oval.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: May 2015
Projected Completion Date:
May 2016
Completion Date:
June 2016
Procurement
Start Date: June 2016
Projected Completion Date:
March 2017
Completion
Date:
January 2018
Construction
Start Date: February 2018
Projected Completion Date:
February 2019
Completion Date: July 2019
Understand how we build parks.
Funding
Funding Sources:
- City Council
- Mayoral
Location
Williamsbridge Oval, Bronx
Reservoir Oval East between Holt Place and Reservoir Place
Community Board: 07
Project Staff
Project Liaison: Katerine Borrome