Shore Park and Parkway Steel Fence Installation, Vegetation Removal and Erosion Control
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct steel fencing, clear vegetation, and control erosion at Shore Park and Parkway.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: September 2013
Projected Completion Date:
June 2015
Completion Date:
August 2017
Procurement
Start Date: August 2017
Projected Completion Date:
May 2018
Completion
Date:
May 2018
Construction
Start Date: July 2018
Projected Completion Date:
July 2019
Completion Date: June 2019
Understand how we build parks.
Funding
Funding Sources:
- Mayoral
- State
Location
Shore Park and Parkway, Brooklyn
Shore Road between 3rd Avenue and 95th Street
Community Board: 10
Project Staff
Project Liaison: Davey Ives
Contact NYC Parks
about this project
Last updated: 01/17/2025