Shore Park and Parkway Steel Fence Installation, Vegetation Removal and Erosion Control

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct steel fencing, clear vegetation, and control erosion at Shore Park and Parkway.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: September 2013
Projected Completion Date: June 2015
Completion Date: August 2017

Procurement

Start Date: August 2017
Projected Completion Date: May 2018
Completion Date: May 2018

Construction

Start Date: July 2018
Projected Completion Date: July 2019
Completion Date: June 2019

Understand how we build parks.

Funding

Total Funding: $1,752,000
Funding Sources:
  • Mayoral
  • State

Location

Shore Park and Parkway, Brooklyn
Shore Road between 3rd Avenue and 95th Street
Community Board: 10

 