Beach 59th Street Playground Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct Beach 59th Street Playground with new play equipment, safety surface, pavements, fencing, spray shower, benches and game tables.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: May 2018
Projected Completion Date: November 2019
Completion Date: November 2019

Procurement

Start Date: November 2019
Projected Completion Date: August 2020
Completion Date: March 2022

Construction

Start Date: June 2022
Projected Completion Date: June 2023
Completion Date: March 2023

Understand how we build parks.

Funding

Total Funding: $5,000,000
Funding Sources:
  • Borough President
  • City Council

Location

Beach 59th St Playground, Queens
Beach 59th Street and Beach 60th Street at Beach Front Road
Community Board: 14

 

Project Staff

Project Liaison: Meira Berkower
Contact NYC Parks about this project