Van Cortlandt Park Indian Fields Ballfields Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the existing natural grass ballfields (Indian Fields) in Van Cortlandt Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: September 2015
Projected Completion Date: October 2016
Completion Date: April 2017

Procurement

Start Date: April 2017
Projected Completion Date: January 2018
Completion Date: November 2018

Construction

Start Date: March 2019
Projected Completion Date: March 2020
Completion Date: May 2022

Understand how we build parks.

Funding

Total Funding: $3,350,000
Funding Sources:
  • City Council
  • Mayoral
  • State

Location

Van Cortlandt Park, Bronx
East 233rd Street between Jerome Avenue and Van Cortlandt Park East
Community Board: 07, 08, 12

 

Project Staff

Project Liaison: Katerine Borrome
Contact NYC Parks about this project