Van Cortlandt Park Playground Construction
-
100% complete
-
100% complete
-
100% complete
This project will construct a playground in Van Cortlandt Park.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: April 2015
Projected Completion Date:
September 2016
Completion Date:
June 2017
Procurement
Start Date: June 2017
Projected Completion Date:
March 2018
Completion
Date:
October 2018
Construction
Start Date: May 2019
Projected Completion Date:
May 2020
Completion Date: July 2020
Understand how we build parks.
Funding
Funding Sources:
- City Council
- Mayoral
- State
Location
Van Cortlandt Park, Bronx
Broadway and Mosholu Avenue
Community Board: 07, 08, 12
Project Staff
Project Liaison: Katerine Borrome
Contact NYC Parks