Van Cortlandt Park Playground Construction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will construct a playground in Van Cortlandt Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: April 2015
Projected Completion Date: September 2016
Completion Date: June 2017

Procurement

Start Date: June 2017
Projected Completion Date: March 2018
Completion Date: October 2018

Construction

Start Date: May 2019
Projected Completion Date: May 2020
Completion Date: July 2020

Understand how we build parks.

Funding

Total Funding: $2,976,000
Funding Sources:
  • City Council
  • Mayoral
  • State

Location

Van Cortlandt Park, Bronx
Broadway and Mosholu Avenue
Community Board: 07, 08, 12

 

Project Staff

Project Liaison: Katerine Borrome
Contact NYC Parks about this project

Last updated: 10/11/2024