Manhattan Basketball Court Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct basketball courts at Seward Park, Thomas Jefferson Park, and Playground 125.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: February 2014
Projected Completion Date: February 2015
Completion Date: April 2015

Procurement

Start Date: April 2015
Projected Completion Date: January 2016
Completion Date: August 2016

Construction

Start Date: September 2016
Projected Completion Date: March 2018
Completion Date: March 2018

Understand how we build parks.

Funding

Total Funding: $937,000
Funding Sources:
  • Borough President
  • City Council
  • Mayoral

Locations

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project