Tompkins Square Playground Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct two playgrounds in Tompkins Square Park with new play equipment, safety surfacing, spray showers, seating, and fencing.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: November 2015
Projected Completion Date: December 2016
Completion Date: June 2017

Procurement

Start Date: June 2017
Projected Completion Date: February 2018
Completion Date: July 2018

Construction

Start Date: September 2018
Projected Completion Date: September 2019
Completion Date: September 2019

Understand how we build parks.

Funding

Total Funding: $2,295,000
Funding Sources:
  • Borough President
  • City Council
  • Mayoral

Location

Tompkins Square Park, Manhattan
East 7th Street and Avenue B
Community Board: 03

 