Spring Street Park Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct Spring Street Park (Soho Square).

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: June 2014
Projected Completion Date: February 2016
Completion Date: February 2016

Procurement

Start Date: February 2016
Projected Completion Date: November 2016
Completion Date: February 2017

Construction

Start Date: March 2017
Projected Completion Date: September 2018
Completion Date: September 2018

Understand how we build parks.

Funding

Total Funding: $4,090,000
Funding Sources:
  • City Council
  • Private

Location

Spring Street Park, Manhattan
6th Avenue betwen Spring Street and Broome Street.
Community Board: 02

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project