Green Central Knoll Public Restroom Building Construction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will construct a new public restroom building and an accessible ramp in Green Central Knoll.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: September 2014
Projected Completion Date: October 2015
Completion Date: September 2016

Procurement

Start Date: September 2016
Projected Completion Date: June 2017
Completion Date: May 2017

Construction

Start Date: June 2017
Projected Completion Date: June 2018
Completion Date: August 2019

Understand how we build parks.

Funding

Total Funding: $3,793,000
Funding Sources:
  • City Council
  • Mayoral
  • Private

Location

Green Central Knoll, Brooklyn
Evergreen Avenue, Noll Street, Central Avenue, Flushing Avenue
Community Board: 04

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project