Green Central Knoll Public Restroom Building Construction
-
100% complete
-
100% complete
-
100% complete
This project will construct a new public restroom building and an accessible ramp in Green Central Knoll.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: September 2014
Projected Completion Date:
October 2015
Completion Date:
September 2016
Procurement
Start Date: September 2016
Projected Completion Date:
June 2017
Completion
Date:
May 2017
Construction
Start Date: June 2017
Projected Completion Date:
June 2018
Completion Date: August 2019
Understand how we build parks.
Funding
Funding Sources:
- City Council
- Mayoral
- Private
Location
Green Central Knoll, Brooklyn
Evergreen Avenue, Noll Street, Central Avenue, Flushing Avenue
Community Board: 04
Project Staff
Project Liaison: Davey Ives
Contact NYC Parks
about this project
Last updated: 11/22/2024