Manhattan Beach Sport Courts Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct the basketball and handball courts in Manhattan Beach Park.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: February 2015
Projected Completion Date:
November 2015
Completion Date:
March 2016
Procurement
Start Date: March 2016
Projected Completion Date:
December 2016
Completion
Date:
January 2017
Construction
Start Date: April 2017
Projected Completion Date:
April 2018
Completion Date: April 2018
Understand how we build parks.
Funding
Funding Source: City Council
Location
Manhattan Beach Park, Brooklyn
Oriental Boulevard and Falmouth Street
Community Board: 15
Project Staff
Project Liaison: Davey Ives
Contact NYC Parks
about this project
Last updated: 11/22/2024