Dome Playground Basketball and Handball Courts Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the basketball & handball courts located in Dome Playground.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: January 2015
Projected Completion Date: November 2015
Completion Date: January 2016

Procurement

Start Date: January 2016
Projected Completion Date: October 2016
Completion Date: February 2017

Construction

Start Date: April 2017
Projected Completion Date: April 2018
Completion Date: March 2018

Understand how we build parks.

Funding

Total Funding: $1,231,000
Funding Sources:
  • City Council
  • Mayoral

Location

Dome Playground, Brooklyn
Dahill Road & 38th Street
Community Board: 12

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project