Dome Playground Basketball and Handball Courts Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct the basketball & handball courts located in Dome Playground.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: January 2015
Projected Completion Date:
November 2015
Completion Date:
January 2016
Procurement
Start Date: January 2016
Projected Completion Date:
October 2016
Completion
Date:
February 2017
Construction
Start Date: April 2017
Projected Completion Date:
April 2018
Completion Date: March 2018