Cypress Hills Playground Synthetic Turf Field Construction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will construct a new synthetic turf multi-purpose athletic field to replace an existing natural turf field at Cypress Hills Playground. The work will include a new perimeter recreation path, reconstructed dugouts, drinking fountains and misting stations.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: April 2016
Projected Completion Date: April 2017
Completion Date: August 2017

Procurement

Start Date: August 2017
Projected Completion Date: April 2018
Completion Date: May 2018

Construction

Start Date: August 2018
Projected Completion Date: November 2019
Completion Date: October 2019

Understand how we build parks.

Funding

Total Funding: $5,464,000
Funding Sources:
  • Borough President
  • City Council

Location

Cypress Hills Playground, Brooklyn
Euclid Avenue, Blake Avenue, Dumont Avenue
Community Board: 05

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 01/17/2025