Bildersee Playground Reconstruction Phase 1
-
100% complete
-
100% complete
-
100% complete
This project will construct a new synthetic turf field and reconstruct the basketball courts at Bildersee Playground.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: March 2016
Projected Completion Date:
June 2017
Completion Date:
June 2017
Procurement
Start Date: June 2017
Projected Completion Date:
March 2018
Completion
Date:
May 2018
Construction
Start Date: September 2018
Projected Completion Date:
September 2019
Completion Date: December 2019
Understand how we build parks.
Funding
Funding Sources:
- Borough President
- City Council
- Mayoral
Location
Bildersee Playground, Brooklyn
Flatlands Avenue between East 81st Street and East 82nd Street
Community Board: 18
Project Staff
Project Liaison: Davey Ives
Contact NYC Parks
about this project
Last updated: 11/22/2024