Frank Golden Park Fields Reconstruction Phase II
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct the athletic fields and park amenities at Frank Golden Park.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: June 2017
Projected Completion Date:
June 2018
Completion Date:
July 2018
Procurement
Start Date: July 2018
Projected Completion Date:
April 2019
Completion
Date:
September 2019
Construction
Start Date: December 2019
Projected Completion Date:
November 2020
Completion Date: August 2021
Understand how we build parks.
Funding
Funding Sources:
- Borough President
- City Council
Location
Frank Golden Park, Queens
15th Avenue and 132nd Street
Community Board: 07
Project Staff
Project Liaison: Meira Berkower
Contact NYC Parks
about this project
Last updated: 11/22/2024