Park of the Americas Synthetic Turf and Playground Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the playground, spray shower and synthetic turf field at Park of the Americas.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: June 2017
Projected Completion Date: June 2018
Completion Date: June 2018

Procurement

Start Date: June 2018
Projected Completion Date: March 2019
Completion Date: June 2019

Construction

Start Date: August 2019
Projected Completion Date: August 2020
Completion Date: July 2020

Understand how we build parks.

Funding

Total Funding: $3,709,000
Funding Sources:
  • City Council
  • Mayoral

Location

Park Of The Americas, Queens
41st Avenue, 103rd Street, 42nd Avenue, 104th Street
Community Board: 04

 

Project Staff

Project Liaison: Meira Berkower
Contact NYC Parks about this project

Last updated: 01/17/2025