Park of the Americas Synthetic Turf and Playground Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct the playground, spray shower and synthetic turf field at Park of the Americas.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: June 2017
Projected Completion Date:
June 2018
Completion Date:
June 2018
Procurement
Start Date: June 2018
Projected Completion Date:
March 2019
Completion
Date:
June 2019
Construction
Start Date: August 2019
Projected Completion Date:
August 2020
Completion Date: July 2020
Understand how we build parks.
Funding
Funding Sources:
- City Council
- Mayoral
Location
Park Of The Americas, Queens
41st Avenue, 103rd Street, 42nd Avenue, 104th Street
Community Board: 04
Project Staff
Project Liaison: Meira Berkower
Contact NYC Parks
about this project