Bowne Park Pond Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the pond in Bowne Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: June 2015
Projected Completion Date: August 2016
Completion Date: June 2018

Procurement

Start Date: June 2018
Projected Completion Date: March 2019
Completion Date: March 2021

Construction

Start Date: March 2021
Projected Completion Date: September 2022
Completion Date: February 2023

Understand how we build parks.

Funding

Total Funding: $2,255,000
Funding Sources:
  • City Council
  • Mayoral