Owl's Head Park Flagpole Installation

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will install a new 25' flagpole in Owl's Head Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: August 2014
Projected Completion Date: February 2015
Completion Date: February 2015

Procurement

Start Date: February 2015
Projected Completion Date: November 2015
Completion Date: July 2015

Construction

Start Date: September 2015
Projected Completion Date: February 2016
Completion Date: March 2016

Understand how we build parks.

Funding

Total Funding: $77,000
Funding Sources:
  • City Council
  • Mayoral

Location

Owl's Head Park, Brooklyn
67th Street and Colonial Road
Community Board: 10

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 10/11/2024