New Dorp Beach Site Restoration in Great Kills Park (Hurricane Sandy)
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct Hurricane Sandy-damaged site amenities, a spray shower and paths at New Dorp Beach in Great Kills Park.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: April 2015
Projected Completion Date:
May 2016
Completion Date:
February 2017
Procurement
Start Date: February 2017
Projected Completion Date:
November 2017
Completion
Date:
March 2018
Construction
Start Date: April 2018
Projected Completion Date:
April 2019
Completion Date: February 2019
Understand how we build parks.
Funding
Funding Sources:
- Federal
- Mayoral
Location
Great Kills Park, Staten Island
Ebbits Avenue and New Dorp Lane along Cedar Grove Avenue
Community Board: 03
Project Staff
Project Liaison: Joseph Homsey
Contact NYC Parks
about this project