New Dorp Beach Site Restoration in Great Kills Park (Hurricane Sandy)

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct Hurricane Sandy-damaged site amenities, a spray shower and paths at New Dorp Beach in Great Kills Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: April 2015
Projected Completion Date: May 2016
Completion Date: February 2017

Procurement

Start Date: February 2017
Projected Completion Date: November 2017
Completion Date: March 2018

Construction

Start Date: April 2018
Projected Completion Date: April 2019
Completion Date: February 2019

Understand how we build parks.

Funding

Total Funding: $1,007,000
Funding Sources:
  • Federal
  • Mayoral

Location

Great Kills Park, Staten Island
Ebbits Avenue and New Dorp Lane along Cedar Grove Avenue
Community Board: 03

 

Project Staff

Project Liaison: Joseph Homsey
Contact NYC Parks about this project

Last updated: 01/17/2025