Jackson Forest Community Garden Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will construct perimeter retaining walls, curbs, steel picket fencing, and a water supply system. Existing side walks and street curbs will be reconstructed.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: October 2014
Projected Completion Date:
December 2014
Completion Date:
February 2015
Procurement
Start Date: February 2015
Projected Completion Date:
November 2015
Completion
Date:
July 2016
Construction
Start Date: September 2016
Projected Completion Date:
September 2017
Completion Date: April 2017
Understand how we build parks.
Funding
Funding Source: City Council
Location
South side of Home Street between Jackson and Forest Avenues
Project Staff
Project Liaison: Katerine Borrome
Contact NYC Parks
about this project
Last updated: 01/17/2025