John J Carty Park Tennis Courts Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct the tennis courts in John J. Carty Park.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: October 2015
Projected Completion Date:
September 2016
Completion Date:
May 2017
Procurement
Start Date: May 2017
Projected Completion Date:
February 2018
Completion
Date:
May 2018
Construction
Start Date: July 2018
Projected Completion Date:
July 2019
Completion Date: November 2020