Flushing Meadows Corona Park Roosevelt Avenue Entrance Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the Roosevelt Avenue entrance to Flushing Meadows Corona Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: September 2014
Projected Completion Date: September 2015
Completion Date: December 2015

Procurement

Start Date: December 2015
Projected Completion Date: September 2016
Completion Date: January 2017

Construction

Start Date: February 2017
Projected Completion Date: August 2018
Completion Date: June 2018

Understand how we build parks.

Funding

Total Funding: $2,324,000
Funding Source: Mayoral

Location

Flushing Meadows Corona Park, Queens
Roosevelt Avenue between Grand Central Parkway and Long Island Rail Road
Community Board: 03, 04, 06, 07, 08

 

Project Staff

Project Liaison: Meira Berkower
Contact NYC Parks about this project

Last updated: 11/22/2024