Flushing Meadows Corona Park Roosevelt Avenue Entrance Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct the Roosevelt Avenue entrance to Flushing Meadows Corona Park.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: September 2014
Projected Completion Date:
September 2015
Completion Date:
December 2015
Procurement
Start Date: December 2015
Projected Completion Date:
September 2016
Completion
Date:
January 2017
Construction
Start Date: February 2017
Projected Completion Date:
August 2018
Completion Date: June 2018
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Flushing Meadows Corona Park, Queens
Roosevelt Avenue between Grand Central Parkway and Long Island Rail Road
Community Board: 03, 04, 06, 07, 08
Project Staff
Project Liaison: Meira Berkower
Contact NYC Parks
about this project
Last updated: 11/22/2024