Benson Playground Asphalt Field and Handball Court Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct the handball court and asphalt field at Benson Playground.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: August 2014
Projected Completion Date:
July 2015
Completion Date:
July 2015
Procurement
Start Date: July 2015
Projected Completion Date:
April 2016
Completion
Date:
March 2016
Construction
Start Date: June 2016
Projected Completion Date:
June 2017
Completion Date: May 2017
Understand how we build parks.
Funding
Funding Source: City Council
Location
Benson Playground, Brooklyn
Bath Avenue between Bay 22nd Street and Bay 23rd Street
Community Board: 11