Queens General Site Work (QG-915M)
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct pavements, fencing and drainage systems at various parks in Queens.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: September 2014
Projected Completion Date:
March 2015
Completion Date:
July 2015
Procurement
Start Date: July 2015
Projected Completion Date:
April 2016
Completion
Date:
June 2016
Construction
Start Date: June 2016
Projected Completion Date:
June 2018
Completion Date: November 2016
Understand how we build parks.
Funding
Funding Sources:
- City Council
- Mayoral
Locations
-
Forest Park, Queens
Myrtle Avenue, Union Turnpike, Park Lane South
Community Board: 05, 05, 06, 09 -
Fort Totten Park, Queens
Fort Totten, Cross Island Parkway, Totten Road to 15 Road
Community Board: 07 -
Hermon A. MacNeil Park, Queens
Poppenhusen Ave. bet. 115 St. and College Pl.
Community Board: 07 -
Rockaway Community Park, Queens
Conch, Sommerville & Norton Basins, Almeda Avenue
Community Board: 14 -
Rockaway Freeway, Queens
Beach 108th Street to Mott Avenue, 83rd Street
Community Board: 14
Project Staff
Project Liaison: Meira Berkower
Contact NYC Parks
about this project
Last updated: 01/17/2025