Playground 52 Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct the play equipment, safety surface, spray shower, fence and landscaping at Playground 52.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: December 2014
Projected Completion Date:
December 2015
Completion Date:
December 2015
Procurement
Start Date: December 2015
Projected Completion Date:
September 2016
Completion
Date:
January 2017
Construction
Start Date: March 2017
Projected Completion Date:
March 2018
Completion Date: March 2018
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Al QuiƱones Playground, Bronx
Kelly Street Between Avenue Saint John and Leggett Street
Community Board: 02
Project Staff
Project Liaison: Katerine Borrome
Contact NYC Parks
about this project
Last updated: 11/22/2024