Playground 52 Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the play equipment, safety surface, spray shower, fence and landscaping at Playground 52.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: December 2014
Projected Completion Date: December 2015
Completion Date: December 2015

Procurement

Start Date: December 2015
Projected Completion Date: September 2016
Completion Date: January 2017

Construction

Start Date: March 2017
Projected Completion Date: March 2018
Completion Date: March 2018

Understand how we build parks.

Funding

Total Funding: $4,242,000
Funding Source: Mayoral

Location

Al QuiƱones Playground, Bronx
Kelly Street Between Avenue Saint John and Leggett Street
Community Board: 02

 

Project Staff

Project Liaison: Katerine Borrome
Contact NYC Parks about this project

Last updated: 11/22/2024