St. Mary's Park Playground West Reconstruction (X045-215MA)

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the basketball and tennis courts, and install play equipment, seating areas, planting beds and trees at St. Mary's Park Playground West.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: March 2015
Projected Completion Date: February 2016
Completion Date: April 2017

Procurement

Start Date: April 2017
Projected Completion Date: December 2017
Completion Date: May 2018

Construction

Start Date: July 2018
Projected Completion Date: July 2019
Completion Date: August 2019

Understand how we build parks.

Funding

Total Funding: $3,700,000
Funding Sources:
  • Borough President
  • City Council
  • Mayoral

Location

St. Mary's Park, Bronx
St. Anns Avenue between East 146th Street and East 148th Street
Community Board: 01

 

Project Staff

Project Liaison: Katerine Borrome
Contact NYC Parks about this project

Last updated: 10/11/2024