Corlears Hook Park Public Restroom Building Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct the public restroom building at Corlears Hook Park.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: December 2015
Projected Completion Date:
April 2017
Completion Date:
October 2018
Procurement
Start Date: October 2018
Projected Completion Date:
June 2019
Completion
Date:
September 2019
Construction
Start Date: September 2019
Projected Completion Date:
March 2021
Completion Date: June 2021
Understand how we build parks.
Funding
Funding Sources:
- Federal
- Mayoral
Location
Corlears Hook Park, Manhattan
Cherry Street between Jackson Street and FDR Drive
Community Board: 03
Project Staff
Project Liaison: Steve Simon