Hunts Point Playground Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct the play equipment, safety surfacing, spray shower, fencing, benches and landscaping in Hunts Point Playground.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: December 2014
Projected Completion Date:
January 2016
Completion Date:
October 2016
Procurement
Start Date: October 2016
Projected Completion Date:
July 2017
Completion
Date:
August 2017
Construction
Start Date: August 2017
Projected Completion Date:
August 2018
Completion Date: May 2019
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Hunts Point Playground, Bronx
Spofford Avenue Between Faile Street and Hunts Point Avenue
Community Board: 02
Project Staff
Project Liaison: Katerine Borrome
Contact NYC Parks
about this project
Last updated: 01/17/2025