Hunts Point Playground Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the play equipment, safety surfacing, spray shower, fencing, benches and landscaping in Hunts Point Playground.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: December 2014
Projected Completion Date: January 2016
Completion Date: October 2016

Procurement

Start Date: October 2016
Projected Completion Date: July 2017
Completion Date: August 2017

Construction

Start Date: August 2017
Projected Completion Date: August 2018
Completion Date: May 2019

Understand how we build parks.

Funding

Total Funding: $3,372,000
Funding Source: Mayoral

Location

Hunts Point Playground, Bronx
Spofford Avenue Between Faile Street and Hunts Point Avenue
Community Board: 02

 

Project Staff

Project Liaison: Katerine Borrome
Contact NYC Parks about this project