Seabury Playground Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will construct a new basketball half-court, fencing, and lighting at Seabury Playground.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: December 2014
Projected Completion Date:
December 2015
Completion Date:
January 2016
Procurement
Start Date: January 2016
Projected Completion Date:
September 2016
Completion
Date:
September 2016
Construction
Start Date: October 2016
Projected Completion Date:
October 2017
Completion Date: September 2017
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Seabury Playground, Bronx
Southern Boulevard between East 173rd Street and East 174th Street
Community Board: 03
Project Staff
Project Liaison: Katerine Borrome
Contact NYC Parks
about this project
Last updated: 01/17/2025