Ranaqua Park Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct the playground and synthetic turf field at Ranaqua Park.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: November 2014
Projected Completion Date:
April 2016
Completion Date:
December 2015
Procurement
Start Date: December 2015
Projected Completion Date:
September 2016
Completion
Date:
September 2016
Construction
Start Date: December 2016
Projected Completion Date:
December 2017
Completion Date: December 2017