Van Alst Playground Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct Van Alst Playground.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: December 2014
Projected Completion Date: November 2015
Completion Date: December 2015

Procurement

Start Date: December 2015
Projected Completion Date: September 2016
Completion Date: June 2016

Construction

Start Date: August 2016
Projected Completion Date: October 2017
Completion Date: June 2017

Understand how we build parks.

Funding

Total Funding: $2,976,000
Funding Source: Mayoral

Location

Van Alst Playground, Queens
29th Avenue and 30th Avenue between 14th Street and 21st Street
Community Board: 01

 

Project Staff

Project Liaison: Meira Berkower
Contact NYC Parks about this project