Van Alst Playground Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct Van Alst Playground.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: December 2014
Projected Completion Date:
November 2015
Completion Date:
December 2015
Procurement
Start Date: December 2015
Projected Completion Date:
September 2016
Completion
Date:
June 2016
Construction
Start Date: August 2016
Projected Completion Date:
October 2017
Completion Date: June 2017
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Van Alst Playground, Queens
29th Avenue and 30th Avenue between 14th Street and 21st Street
Community Board: 01
Project Staff
Project Liaison: Meira Berkower
Contact NYC Parks
about this project
Last updated: 01/17/2025