Sol Lain Playground Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the entire playground including play equipment, spray shower, basketball court, multi-purpose play area, benches, fences, drainage, water supply, security lighting, sports lighting and landscaping.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: December 2014
Projected Completion Date: December 2015
Completion Date: December 2015

Procurement

Start Date: December 2015
Projected Completion Date: September 2016
Completion Date: July 2016

Construction

Start Date: August 2016
Projected Completion Date: October 2017
Completion Date: September 2017

Understand how we build parks.

Funding

Total Funding: $2,878,000
Funding Source: Mayoral

Location

Sol Lain Plgd, Manhattan
Adjacent to P.S. 134 between Henry Street and East Broadway
Community Board: 03

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project