Sol Lain Playground Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct the entire playground including play equipment, spray shower, basketball court, multi-purpose play area, benches, fences, drainage, water supply, security lighting, sports lighting and landscaping.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: December 2014
Projected Completion Date:
December 2015
Completion Date:
December 2015
Procurement
Start Date: December 2015
Projected Completion Date:
September 2016
Completion
Date:
July 2016
Construction
Start Date: August 2016
Projected Completion Date:
October 2017
Completion Date: September 2017
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Sol Lain Plgd, Manhattan
Adjacent to P.S. 134 between Henry Street and East Broadway
Community Board: 03
Project Staff
Project Liaison: Steve Simon
Contact NYC Parks
about this project
Last updated: 11/22/2024