James Weldon Johnson Playground Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct the playground, active recreation and joint operated playground with the adjacent school.
Project Timeline
Design
Assigned & Start Date: January 2015
Projected Completion Date:
January 2016
Completion Date:
January 2016
Procurement
Start Date: January 2016
Projected Completion Date:
October 2016
Completion
Date:
September 2016
Construction
Start Date: November 2016
Projected Completion Date:
February 2018
Completion Date: February 2018