James Weldon Johnson Playground Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the playground, active recreation and joint operated playground with the adjacent school.

Project Timeline

Design

Assigned & Start Date: January 2015
Projected Completion Date: January 2016
Completion Date: January 2016

Procurement

Start Date: January 2016
Projected Completion Date: October 2016
Completion Date: September 2016

Construction

Start Date: November 2016
Projected Completion Date: February 2018
Completion Date: February 2018

Understand how we build parks.

Funding

Total Funding: $4,397,000
Funding Source: Mayoral

Location

James Weldon Johnson Playground, Manhattan
South of East 115th Street between Third Avenue and Lexington Avenue
Community Board: 11

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 01/17/2025