Grassmere Playground Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the play equipment, swings, landscaping, and sitting areas in Grassmere Playground.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: February 2015
Projected Completion Date: December 2015
Completion Date: January 2016

Procurement

Start Date: January 2016
Projected Completion Date: October 2016
Completion Date: July 2016

Construction

Start Date: November 2016
Projected Completion Date: May 2018
Completion Date: November 2017

Understand how we build parks.

Funding

Total Funding: $3,844,000
Funding Source: Mayoral

Location

Grassmere Playground, Queens
Hanson Court between Grassmere Terrace and Briar Place
Community Board: 14

 

Project Staff

Project Liaison: Meira Berkower
Contact NYC Parks about this project