Levy Playground Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct Levy Playground with a new basketball court, play equipment, safety surfacing, interactive water features and landscaping.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: December 2014
Projected Completion Date: December 2015
Completion Date: December 2015

Procurement

Start Date: December 2015
Projected Completion Date: September 2016
Completion Date: November 2016

Construction

Start Date: November 2016
Projected Completion Date: May 2018
Completion Date: May 2018

Understand how we build parks.

Funding

Total Funding: $1,988,000
Funding Source: Mayoral

Location

Levy Playground, Staten Island
Jewett Avenue and Castleton Avenue
Community Board: 01

 

Project Staff

Project Liaison: Joseph Homsey
Contact NYC Parks about this project

Last updated: 11/22/2024