Levy Playground Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct Levy Playground with a new basketball court, play equipment, safety surfacing, interactive water features and landscaping.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: December 2014
Projected Completion Date:
December 2015
Completion Date:
December 2015
Procurement
Start Date: December 2015
Projected Completion Date:
September 2016
Completion
Date:
November 2016
Construction
Start Date: November 2016
Projected Completion Date:
May 2018
Completion Date: May 2018
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Levy Playground, Staten Island
Jewett Avenue and Castleton Avenue
Community Board: 01
Project Staff
Project Liaison: Joseph Homsey
Contact NYC Parks
about this project
Last updated: 11/22/2024